SIPPO LAKE DREDGING PROJECT
PROJECT COMPLETION REPORT
Prepared by:
ms consultants, inc.
engineers, architects, and planners
Canton, Ohio
Prepared for:
The Stark County Park District
Canton, Ohio
February 1999
|
TABLE OF CONTENTS
Introduction
Background of Project
Bidding Process
Site Preparation and Plant Assembly
Year One Operation (1997)
Year Two Operation (1998)
Final Cost Summary
Project Summary and Evaluation
Attachments
Figures
Site Photographs
List of Reports
Key Personnel Involved in Sippo Lake Dredging Project
SIPPO LAKE DREDGING PROJECT
PROJECT COMPLETION REPORT
Introduction
Sippo Lake is a 107 acre lake
located in Perry Township, Stark County, Ohio (see Figure 1). The lake was constructed in the late
1800s. The lake is impounded by a 445
foot earthen dam with a concrete outlet structure designed to maintain a
constant water pool. Sippo Lake and a
portion of the land surrounding the lake are owned and operated by the Stark
County Park District. Primary
water-based recreation uses are boating (small boats) and fishing, both from
boats and from a fishing dock. Swimming
is not permitted.
The lake has a large watershed
area of 2,789 acres. The intense
development of this watershed area has contributed to sediment flow to Sippo
Lake. Through the years, the depths of
the lake have decreased dramatically.
Based on historic data and recent sediment measurements, there appeared
to be an average of six feet of pre-1900 organic sediments over the till lake
bottom. Above these pre-1900 deposits,
there was roughly eight feet of semi-suspended organic sediments covered with
an average of about five feet of relatively clear water. The pre-dredging bathymetry of Sippo Lake,
as measured in 1995, is shown in Figure 2.
The mean depth of the lake was about 5.1 feet, with a maximum depth of
14 feet in a small hole near the southern end of the lake.
The shallowness of Sippo Lake has
been recognized as an impediment to the recreational use of the lake. In some years, explosive growth of large macrophytes
has covered virtually the entire surface of the lake and adversely affected
boating use. By the late 1980s,
lake users were becoming increasingly concerned that the infilling of the lake
would eventually make it unusable for recreation. Since Sippo Lake is one of Stark County’s most important
recreation facilities, the loss of the lake would be a major loss for
recreation in the Canton area.
Background of Project
The need to dredge Sippo Lake had
been recognized for many years. In
1990, the Stark County Park District received a grant from U.S. EPA Clean Lakes
Program to prepare a Phase I Diagnostic Feasibility Study for the lake. This study was prepared through a
cooperative effort involving the Park District, the Ohio EPA, and the Northeast
Ohio Four County Organization (NEFCO).
One key element of the study was
the formation of a Technical Advisory Committee for Sippo Lake
Restoration. The Advisory Committee
involved a diverse group of people, including representatives from key
governmental agencies, (OEPA, ODNR, and the Army Corps of Engineers), local
academic institutions (Kent State University Biological Sciences Department),
and local citizens. After extensive
study and discussion, the Advisory Committee established a list of key actions
that should be undertaken to restore Sippo Lake. One of the key actions identified by the Committee was the
selective dredging of the lake. At the
time of the original report in 1992, the cost of the dredging program (200,000
cubic yards) was estimated at approximately $1.1 million. Details regarding the Phase I study and
recommendations are detailed in the report Sippo Lake Phase I
Diagnostic-Feasibility Study (September 1992).
As a result of the Phase I study,
the Park District secured lake restoration funding from the U.S. EPA (314 and
319 programs) and from the State of Ohio.
Following the completion of the Phase I report, the Park District hired
a consultant to develop detailed plans for various elements of the restoration
program, including the dredging.
Through 1993 and 1994, Fugro East worked on the various lake restoration
elements. Through these efforts, a number of tasks were completed, including
purchase of a macrophyte harvester and
installation of fiber roll materials to serve as biological sediment barriers
near the inflows of several tributary streams.
During this period, plans were
developed for lake dredging. These
plans were based on using a standard “dredge and dispose” methodology requiring
large and deep containment basins. However, as work proceeded, two crucial
problems became apparent. With sampling
of the lake bottom material, it was found that the material had extremely poor
settling characteristics, so the settling area for the dredging material would
require an extremely long retention time.
Second, it was found that the soil characteristics in the site for the
settling pond were very unfavorable.
Construction of the high dikes for a traditional settling area would
require expensive site preparation and use of geotextiles for stability. The details regarding the original settling
basin design were presented in a report titled Dredged Material Containment
Area Preliminary Design Report (September 1994).
Planning for the containment basin
proceeded to the point of advertising bids for construction of the settling
basin in the fall of 1995. However, at
this point, the Park District made the determination that the cost of
constructing the containment basin (over $800,000) was excessive and would make
it impossible to complete the dredging project with available funds. Additionally, the estimated time to complete
the project (3 dredging seasons) was not considered acceptable.
The Park District then decided to
investigate if any alternative technologies exist that could reduce the cost of
lake dredging. Working with ms
consultants, inc., initial contacts were made with the aggregate industry
(sands and gravels) since this industry uses dredges and mechanical dewatering
measures. While mechanical dewatering
is possible in a lake dredging application, it was determined that the costs of
the required equipment alone (probably near $2 million) and the labor requirements
for plant operation makes this option infeasible.
Investigations were also made
regarding the potential to adapt technologies used to dewater hazardous waste
materials. This technology had been
used on small dredging projects (golf course ponds, etc.) in the western United
States. Companies were providing this
service on a “turnkey” basis. However,
quoted costs approaching or exceeding $10 per cubic yard were still to high to
be feasible for Sippo Lake.
In late 1995, ms learned of lake
restoration work being done in Florida by BCI (Bromwell & Carrier
Inc.). Research publications indicated
that BCI was working on lake projects with sediment characteristics similar to
the highly organic materials found at Sippo and had developed an advanced
sediment dewatering process that could be applicable for these materials. In late 1995, ms contacted BCI to determine
if the new technology might be suitable for this project. After some discussion, ms and BCI developed
an initial feasibility study (Sippo Lake - Initial Feasibility of Rapid
Sediment Dewatering, March 1996).
This study evaluated the feasibility of the BCI process for Sippo
Lake. In the early 1990s, the Florida
Institute of Phosphate Research (FIPR) patented a rapid dewatering process for
fine-grained materials. This process
utilized both polymer flocculation and a mechanical dewatering device. While initially developed for dewatering
phosphatic clays, research suggested that the process may also work on
fine-grained lake sediments. At this
time, the process had never actually been tried on a full-scale project. Initial lab testing of the Sippo Lake
sediments indicated that the material would flocculate well and dewater rapidly
with this process.
One key theoretical advantage of
this dewatering process was the cost savings associated with the preparation of
the drying area. The process did not
involve construction of the deep settling ponds. Instead, only low berms (about 5 to 6 feet) were to be build to
confined the pumped dewatered material.
Since the material would already be partially dewatered and would
flocculate quickly, the high walls and long detention times associated with
conventional dredging would be avoided.
Based on the initial tests, an
initial project design was formulated with the following key elements:
1. Hydraulic
dredging would be conducted at a rate of 2,500 cubic yards/day for 120
days. Dredge pumping rate would be
approximately 2,000 gpm.
2. Dredged
sediment, at approximately 5 percent solids, would be pumped to the dewatering
plant located on the northwest side of the lake.
3. Dredged
sediment would be flocculated and screened producing a thickened sediment at
approximately 15 percent solids. Clean
water resulting from the dewatering process would be returned to the lake.
4. Thickened
sediment would be sequentially pumped to low-walled drying areas at a rate of
approximately 1,500 cubic yards per day.
5. Sediment
would be allowed to air dry and then “worked” (turned over) to enhance drying.
Following the initial feasibility
study, the Park District directed ms and BCI to prepare an actual plan for the
dredging project. The results are
documented in the report Sippo Lake Sediment Removal Study: Sediment Removal
and Disposal Plan (August 1996).
This report provided detailed analyses of sediment characteristics and
discussed various design alternatives.
The report recommended a particular polymer material (Percol 455) and
indicated that the estimated cost of dredging approximately 300,000 cubic yards
of material would be $1,305,000, exclusive of planning and design costs. These costs were more fully detailed in
Table 1.
TABLE 1
PRELIMINARY COST
ESTIMATES - AUGUST 1996
(exclusive of
planning and engineering costs)
Major
Cost Components |
Cost
Estimate |
Berm Construction |
$50,000 |
Hydraulic Dredging |
$600,000 |
Dewatering Plant Operations |
$478,000 |
Drying Operations |
$50,000 |
Site Reclamation, Wetland
Mitigation |
$125,000 |
Total Estimated Cost |
$1,305,000 |
In late 1996, the Park District
directed ms and BCI to prepare detailed construction plans for the various work
elements included in the dredging project, including the design and assembly of
the sediment dewatering plant and the construction of the sediment disposal
area. These plans were essentially
completed in early 1997. Figure 2 shows
the original plan for the drying beds.
Figure 3 shows the original plan for the sediment dewatering plant.
Also, in early 1997, the permit
process was completed. The various
permits associated with the project included:
401 Permit - The OEPA issued the original water quality
certification on this project on June 19, 1995. This original certification was for a conventional dredging
process.
404 Permit - The Corps of Engineers originally issued a 404
permit for conventional dredging on July 13, 1995. On October 31, 1996, the COE approved a “minor modification” of
the original permit to allow the use of the sediment dewatering process, and
also modified the wetland mitigation concept.
The Corps of Engineers advised the Park District that the approval of
this minor modification covered both the 401 and the 404 permit. The 404/401 permits also required wetland
mitigation steps, with a mitigation completion date of December 31, 2000.
NPDES Permit - On January 23, 1997, the Ohio EPA indicated that a
NPDES permit would not be required for the dewatering plant.
Stormwater
Prevention Plan - On May 21, 1997,
OEPA approved the Stormwater Prevention Plan (SWP3) for the sediment drying
area.
Permit to
Install (PTI) - On June 9, 1997, Ohio
EPA issued a “Permit to Install” covering the sediment dewatering plant.
Bidding Process
Bids for the project were
advertised in January 1997. A variety
of separate bids were required for dredging, equipment acquisition, drying bed
preparation, and dewatering plant assembly.
The key bids that were awarded are listed in Table 2.
TABLE 2
SIPPO LAKE
DREDGING - BIDS AWARDED IN 1997
Item |
Low Bidder |
Bid Amount |
Comments |
Dredging |
Midwest Dredge Floyds Knobs, IN |
$441,125 |
Included mobilization; basic
dredging cost of $1.36 per cubic yard; 300,000 CY of hydraulic dredging. |
Pumps |
Midwest Dredge Floyds Knobs, IN |
$66,521 |
Covers rental of feed pumps and
thickened solids pump for a six month period. |
Rotary Screen |
Vulcan Industries Inc. Missouri Valley, IA |
$76,000 |
The rotary screen is a major
part of the sediment dewatering plant. |
Clearing and Grubbing |
Clearcut Land Service Inc. North Canton, OH |
$38,480 |
Included removal of vegetation
necessary to allow construction of drying areas. |
Site Grading |
Oakes Land & Excavating Massillon, OH |
$111,668 |
Original construction of berms
for drying areas. |
Plant Assembly |
Standard Plumbing & Heating Canton, OH |
$98,430 |
Included providing a variety of
piping, valves and other equipment needed for the plant; and the assembly of
the plant. |
Bulldozer Rental |
Mahnen Equipment Company |
$10,200 |
Rental of low ground pressure
dozer for 6 months. |
Flocculent |
Allied Colloids Inc. Suffolk, VA |
$96,000 |
Cost of $1.50 per pound for
64,000 pounds. |
Flocculent Feed System |
Allied Colloids Inc. Suffolk, VA |
$12,000 ($2,000/mo.) |
Covers rental for 6 month
period. |
Year One Operation (1997)
Many operational problems were
faced during 1997. Because of these
problems, it was not possible to complete the dredging in one season as
originally planned. The major problems
faced in 1997 are summarized below:
Late Start-up - The original bid opening for plant assembly was March
25. This would have allowed the
District to build the plant in April and be pumping in May. However, because of the unfamiliarity of the
project, all the potential assembly bidders withdrew, so the District had to
re-bid, delaying assembly until May and start-up until June 15, 1997. This delayed the project approximately 30-40
days. The importance of this delay
became increasingly apparent later in the year.
Problems with
Polymer Delivery System - By the
beginning of June, the plant was ready for operations. The first two weeks of June were utilized
for a shakedown and testing period, with actual operations starting on June
15. Within the first few weeks of
operation, it became apparent that there was a substantial problem with the
polymer delivery system. The polymer
delivery system was designed to allow continual plant operation. However, in reality, the polymer system was
unable to produce material as fast as needed.
While the plant could produce about 20 gallons per minute (gpm) of
polymer material, the operation typically consumed about 28 to 30 gpm. This higher rate was needed to provide
adequate flocculation of material.
Since polymer was consumed faster than it could be produced, this made
it necessary to operate the system in an “on-off” manner. The dredger and plant would run until the
polymer was depleted, then both would be forced to wait until more polymer
material was mixed. In June 1997, the
plant typically operated only 3.5 to 5 hours per day. This continued until the plant was modified with additional
polymer storage tanks in mid-August.
This modification allowed the operators to mix polymer during the night,
providing a larger supply of material in the morning. With this change, after August 16, the plant was able to operate
about 7 hours per day, allowing much higher production.
The actual polymer
usage rates in the field were considerably higher than the rates predicted by
laboratory analyses and appeared to be due to the nature of the dredged sediments. This may be a typical situation in sediment
dewatering. Also, in practice, material
was sent to the drying beds at a lower solids percentage than was predicted by
laboratory analyses.
Rotary Screen
Problems - Until field modifications
were made, mechanical breakdowns of the rotary screen were a major
difficulty. Multiple weld and bolt
breaks were experienced. Repair of the weld and bolt problems delayed the
project about 5-6 days.
Drying Bed
Management Problems - As a result of
this project, we have learned that the management of the drying beds is a more
intensive operation than originally anticipated. This is particularly true because material was sent to the beds
at the lower solids percentage than originally anticipated. For bed management, it is necessary to have
at least one bulldozer in operation at all times. Further, the size of the original bulldozer that was leased was
inadequate. This was further
complicated by the poor mechanical condition of the original unit. The ongoing breakdowns of this unit caused
some project delays, affecting the project by at least 3-5 days.
To some degree, bed
management problems may be an unavoidable aspect of utilizing this system of
sediment dewatering in a northern climate with limited bed capacity. If the polymer feed capacity had allowed
processing the material at a higher rate in the early part of the season, it is
likely that the beds would have been filled to a point that operations would
have stopped to allow drying. Given the
late start date, it is very possible that two dredging seasons were necessary,
even without the polymer feed problems.
The late start date
caused another problem associated with Ohio climate. As work proceeded, it became apparent that dredging would not be
completed by the original October completion date. A decision was made to continue dredging as long as possible,
through November and possibly into December.
However, in October, it became apparent that the change in weather
(shorter daylight, cooler nights) had a dramatic effect on the dewatering
characteristics of the sediments. In
mid-October, the drying of the material essentially stopped, making it
impossible to continue dredging due to the lack of drying bed space.
Sediment
Qualities - The nature of the lake
sediments proved to be more variable than anticipated, and the different
materials react very differently with the polymer. In some areas, this required the dredger to utilize the
“undercut” dredging technique that provided a material that was more conducive
to flocculation. This procedure is much
slower than normal dredging. At the
extreme northern end of the lake, the very fine material encountered reacted
poorly with the flocculent, requiring slow dredging rates. This also delayed the project. In a few areas, the dredging plan was
revised to avoid areas that were known to contain material that would react
poorly with the flocculent.
The actual dredging period for
1997 extended from June 15 through October 14, a total of 120 days. During this time, the dewatering plant
operated a total of 579 hours over 104 working days. This averages 5.5 hours of plant operation per day. Daily operation hours increased in August,
when 2 extra polymer storage tanks were installed.
Based on in-lake measurements,
about 152,700 cubic yards of material were dredged in 1997, or about 264 cubic
yards per hour of plant operation. This
was approximately 50% of the total dredging project.
Year Two Operation (1998)
Plant and dredging operations were
much smoother in 1998. Before work was
started, most of the dewatered material already in the drying beds was removed
by pushing material to the sides of the beds.
The beds were then regraded and reconfigured to allow more efficient bed
management. Also, two additional
polymer storage tanks were added before the start of 1998 operations. This further increased the operators’
ability to make and store mixed polymer materials overnight. By having large quantities of polymer
available, the dredgers were able to operate on a much more continuous and
efficient schedule. In 1997, the plant
only operated about 5.5 hours per day out of a 10 to 12 hour working day, meaning
the plant was in operation less than 50% of the time. In 1998, the working day was shortened to 8 hours, but the plant
was able to operate 6.3 hours a day, or about 75% of the time. Since some downtime is inherent in the
process (dredge equipment downtime, plant maintenance, drying bed problems) the
75% operation may be about as good as can be accomplished.
Plant and dredging working
schedules were also adjusted. In 1997,
the basic attempted working schedule was 10 to 12 hours per day, 7 days per
week. In 1998, the basic schedule was 8
hours per day, 6 days a week. The
scheduled off day each week allowed plant maintenance, and also provided a
better balance between plant operation and material drying in the beds.
For 1998, the dredging period ran
from May 4 to September 20, a total of 110 calender days. During the last month of the operation, a
major change was made in plant operations.
The rotary screen was bypassed, and material was treated and pumped directly
to the beds without the screening process.
While some extra water was sent to the beds, it appeared that the
flocculated material reached the beds in better condition and settled faster
than it had when it passed through the rotary screen. The water separated quickly from the material in the beds. The results of this experiment suggest that
the extra disruption of the forming flocculents that occurs through the screen
and the thickened solids pump may actually result in retarding the settling of
the treated sediment.
Also, in the last weeks of the
project, a mechanical dredge was brought in to clean out the in-lake settling
areas that were created with bioengineering fiber rolls at the stream
outlets. This work was not part of the
original dredging plan. The mechanical
dredge was also used to remove material near the northwest corner of the lake
that could not be hydraulically dredged due to the presence of extensive
debris, including logs and trash.
In 1998, the plant operated 84
days out of a dredging period of 110 days.
The plant operated a total of 527 hours, or about 6.3 hours per working
day. A total of 150,600 yards of
material was dredged in 1998, or about
286 yards per hour of plant operation.
Table 3 provides an overall
chronology of the Sippo Lake dredging program, beginning with the initial
planning and continuing through the dredging process.
TABLE 3
CHRONOLOGY OF
EVENTS - SIPPO LAKE DREDGING PROJECT
Year |
Month |
Event |
1988 |
December 29 |
First meeting of Sippo Lake
Citizens’ Advisory Board |
1989 |
December |
Report on bathymetric survey by
Crossroads RC&D |
1990 |
February 6 |
Sippo Lake Technical Advisory
Committee holds first meeting, includes former Citizens’ Advisory Board. |
1991 |
September 19 |
Alternative dredging plans
presented to Advisory Committee. |
1991 |
December 11 |
Dredging plans presented to
public, including Lakeshore Homeowners Association. |
1992 |
January 29 |
After several revisions, plan
“F” is developed and presented to Advisory Committee. |
1992 |
January |
Application for “Phase II”
funding prepared with Ohio EPA and submitted to USEPA. |
1992 |
June |
Original wetland delineation
study prepared by Ohio EPA. |
1992 |
September |
Draft “Sippo Lake
Diagnostic-Feasibility Study” published. |
1992 |
October |
USEPA approval of Section 319
and Section 314 grants. |
1993 |
February |
Final Diagnostic-Feasibility
Study completed. |
1993 |
September |
Wetland delineation report by
Fugro completed. |
1994 |
September |
“Dredged Material Containment
Area Preliminary Design Report” completed by Fugro. |
1994 |
October |
Approval of COE 404 permit for
dredging, fill of wetland areas. |
1994 |
December |
Ohio EPA approval of 401 Water
Quality Certification, includes restoration of 3.6 acres of wetland on-site
and 1.9 acres either on-site or off-site. |
1995 |
September |
Park District asks ms
consultants to evaluated new dredging technologies, ms contacts considers
various potential methods. |
1995 |
December |
ms identifies polymer
flocculation technique being developed by BCI of Lakeland, Florida as the
most promising procedure, Park District hires ms/BCI to evaluate feasibility. |
1996 |
January |
ms/BCI collects lake bottom
samples for sediment analysis. |
1996 |
March |
“Initial Feasibility of Rapid
Sediment Dewatering” report completed by ms/BCI, identifies polymer
flocculation as the preferred technology. |
1996 |
May |
Approval of ODNR Natureworks
grant. |
1996 |
October |
Modified dredging and wetland
plan approved by Corps of Engineers, allows use of sediment dewatering. |
1996 |
August |
“Sippo Lake Sediment Removal
Study: Sediment Removal and Disposal Plan” completed by ms/BCI. |
1996 |
December |
Bids out for lake dredging,
awarded to Midwest Dredging. |
1997 |
January |
Bid out for rotary screen,
awarded to Vulcan. |
1997 |
March |
Bids out for assembly of
dewatering plant, no responsive bidders. |
1997 |
April |
Rebid for assembly of dewatering
plant, awarded to Standard Plumbing. |
1997 |
May |
Dave Price hired as dewatering
plant operator. |
1997 |
May |
Standard Plumbing completes
assembly of dewatering plant. |
1997 |
May |
Plant equipment delivered to
site. |
1997 |
June |
“Permit to Install” approved by
Ohio EPA. |
1997 |
June |
“Shakedown” period for
dredging/dewatering plant. |
1997 |
June |
Oakes completes grading of
drying beds. |
1997 |
June |
First official dredging day,
June 16. |
1997 |
June |
Bob Fonte & Bill Malson
present paper on project at “Connecting Ohio Watersheds” conference. |
1997 |
October |
Dredging work halted due to lack
of drying cell space and deteriorating weather conditions. |
1998 |
May |
Restart of dredging work. |
1998 |
March |
Bids for regrading of drying
beds, awarded to Oakes. |
1998 |
August |
Hydraulic dredging completed. |
1998 |
September |
Mechanical dredging of marina
area and baffle areas completed. |
Final Cost Summary
The following table compares
actual project costs to the original estimates in the BCI report of August
1996. This comparison is being done for
planning purposes for future projects.
The costs shown on the table are subject to change based on final site
reclamation and management costs and credits for sale of salvage equipment
items (rotary screen, etc.) that have not been finalized as of February
1999. These changes should be
relatively minor. The purpose of this
table is not to provide an exact accounting of project costs, but instead is
intended just to provide a comparison of estimated costs versus actual
costs. The table is consistent with
the cost summary provided to the Park Board on September 1998.
The actual dredging construction
and operation cost of $1,667,494 is about $364,000 (28%) higher than the
original cost of $1,303,000. The extra cost is primarily a result of operating
two years instead of one, and also the extra costs associated with cleaning and
reshaping beds before the second year.
This second year of dredging was forced because the plant could not
process material as fast as originally hoped, and the sediment drying in the
beds was slower than anticipated due to the higher percentage of water pumped
to the drying areas.
TABLE 3
ORIGINAL
PLANNING ESTIMATES COMPARED TO ACTUAL COSTS
MAJOR COST COMPONENT |
1996 COST EST. |
COST/ C.Y. (300,000) |
FINAL COST |
COST/C.Y. (303,354) |
COMMENTS |
Berm construction |
$50,000 |
$0.17 |
$139,883 |
$0.46 |
Berm construction cost
exceeded original estimate, possibly because of higher local construction
costs and high costs associated with poor soil conditions. Approximately 20 acres of drying beds were
graded. |
Hydraulic dredging |
$600,000 |
$2.00 |
$582,067 |
$1.92 |
Even with extensive
“downtime” costs in 1997, dredging cost is still close to original
estimate. Does not include mechanical
dredging. Total of 303,000 CY of
material dredged. |
Dewatering plant and
cell operations |
$528,000 |
$1.76 |
$820,544 |
$2.70 |
Higher costs were due to two years of
operation, rather than one. Includes
costs involved with regrading drying beds prior to second dredging season. Includes plant assembly, polymer, payroll. |
Site reclamation |
$125,000 |
$0.42 |
$125,000 |
$0.42 |
Some reclamation has
already been accomplished under operations work. Reclamation cost will depend on ultimate decisions regarding
site (for example, preparation for education building). Under the 404 permit requirements,
mitigation must be complete by 12/31/00. |
TOTAL HYDRAULIC
DREDGING CONSTRUCTION AND OPERATIONS |
$1,303,000 |
$4.34 |
$1,667,494 |
$5.50 |
Includes $125,000
for site reclamation, actual costs not determined. Does not include any income from salvage (sale of rotary
screen). |
Design/construction
management |
$202,129 |
$0.67 |
$202,129 |
$0.67 |
BCI estimate did not
include design costs, design and management costs added in to BCI estimate to
allow total comparison. |
Mechanical dredging |
|
|
$26,200 |
|
Approximately 2,000
c.y., not considered in original estimate. |
TOTAL HYDRAULIC AND
MECHANICAL DREDGING, INCLUDING DESIGN AND MECHANICAL DREDGING |
$1,505,129 |
$5.02 |
$1,895,823 |
$6.25 |
Includes $125,000 for
site reclamation, actual costs for reclamation not determined. |
FINAL OPERATIONS SUMMARY
Table 5 compares the
final operations results to the original estimates developed in 1996. The total cubic yards dredged met the
original goal. The actual hours of
plant operation was slightly less than the original estimate. However, these hours were distributed over
many more days than originally estimated due to the extensive downtime
experienced in 1997.
TABLE 4
FINAL OPERATIONS
SUMMARY
PARAMETER |
1997 |
1998 |
TOTAL |
BCI ORIGINAL ESTIMATE |
COMMENTS |
Total cubic yards
dredged |
152,767 |
150,587 |
303,354 |
300,000 |
Estimates based on lake
soundings. Does not include yardage
dredged mechanically |
Total hours plant
operation |
579 |
527 |
1,106 |
1,200 |
Original report
anticipated 120 days @ 10 hours per day.
|
Total days plant
operated |
104 |
84 |
188 |
120 |
Original report
anticipated 10 hours of plant operation per day. This was not possible due to the polymer delivery system
problems. |
Total duration of
operation - days |
120 |
110 |
230 |
180 |
Original report
anticipated completion of dredging in 6 month dredging period. This could not be accomplished. However, even under best conditions,
drying bed operations may have constrained ability to complete project in one
season. |
Hours operation per day |
5.5 |
6.3 |
5.9 |
10.0 |
In 1997, plant operated
5.5 hrs./day in a 10 to 12 hour working day.
In 1998, the plant operated 6.3 hours per day in an 8 hour working
day. Achieving average of 6 hours out
of an 8 hour day (75%) may be as good as possible. |
Yards dredged per hour
of plant operation |
263.8 |
285.7 |
274.3 |
250.0 |
Possibly solids % in
dredged material higher than expected, may account for higher number. If not constrained by plant, Midwest
claims to be able to dredge 365 cy per hour. |
Total pounds of polymer
utilized |
38,575 |
32,403 |
70,978 |
64,000 |
Some polymer lost in
1997 due to downtime, operations more efficient in 1998. Does not include polymer used for
mechanical dredging in 1998. |
Cost of polymer
utilized |
$57,863 |
$48,605 |
$106,467 |
|
Does not include
polymer used for mechanical dredging in 1998. |
Polymer cost per yard
dredged |
$0.38 |
$0.32 |
$0.35 |
|
|
Estimated wt. of dry
solids (tons) |
12,962 |
12,807 |
25,769 |
|
Estimate based on
original lab tests of sediments, should be considered as rough estimate. |
Estimated wt. of dry
solids (million lbs.) |
25.9 |
25.6 |
51.5 |
|
|
Polymer used per ton of dry
solids |
3.0 |
2.5 |
2.8 |
1.0 to 2.0 |
Higher usage rate
necessary to achieve flocculation, meant that polymer system could not “keep
up” until auxiliary tanks added in 1998.
Operation more efficient in 1998. |
Average percent solids of dredge
output |
|
|
5.2% |
4.5% |
Solids output of dredge
higher than forecast. |
Sediment removed by mechanical
dredging |
|
2,000 CY |
2,000 CY |
|
Not included in
original dredging plan. |
Project Summary and
Evaluation
* The
basic goal of removing 300,000 cubic yards of sediment material from Sippo Lake
was met. Lake depths were substantially
increased to the point where a large portion of the lake has a depth of 10 feet
or more, and this should help control the spread of aquatic macrophytes over
the total lake surface.
* The
polymer sediment dewatering process was a viable solution to the problem faced
at Sippo Lake. Based on observations of
untreated material occasionally sent to the drying beds, it is likely that this
material would have taken an exceptionally long time to settle and dewater
without some kind of treatment. It is
questionable if adequate settling could have been accomplished with a
conventional drying bed system.
* The
final project cost of $6.25 per cubic yard of material dredged is within the
range of costs normally associated with dredging projects of this size.
* One
of the major problems faced in dewatering plant operation was the inability of
the polymer delivery system to provide adequate quantity of material. The actual rate of polymer usage required to flocculate the material was far higher than
predicted in lab tests. Future projects
should allow a large “margin of error”
for polymer delivery, since the extra cost involved in a larger polymer
system would be minimal in comparison to costs associated with project delays.
* Drying
bed operations are labor intensive. For
a project of this size, a full-time bulldozer operator is mandatory. The size of the machine required should also
be carefully evaluated. Machines that
are too small cannot keep up with the required material handling, but machines
that are too large are too heavy to operate in the wet conditions that are
present.
* The
position of plant operator is a key position to fill. It is important that the operator have some familiarity with
similar types of polymer systems, such as are commonly found in wastewater
treatment facilities. The plant
operator should also be able to make independent operational decisions without
continual supervision. The extra money
spent to hire a skilled operator will result in long-term savings to the
project.
* In
northern climates, the use of this type of polymer dewatering is essentially
limited to the months from May through October.
* While
the flocculation process works, the rotary screen system may not be the most
appropriate method. During operation,
it became increasingly clear that the flocculated material should be handled
and disrupted as little as possible.
The rotary screen and associated pump tended to disrupt the flocculation
process.
Figures
Figure 1 Project
Location Map
Figure 2 Lake
Bathymetry Before Dredging
Figure 3 Plan
for Drying Beds (Original)
Figure 4 Plan
for Sediment Dewatering Plant (Original)
Figure 5 Sippo
Lake Dredged Areas
SITE PHOTOGRAPHS
LIST OF REPORTS
The following reports were
prepared as part of the Sippo Lake dredging project:
Fugro
East Inc., 1994, Dredged Material Containment Area Preliminary Design Report,
Prepared for the Stark County Park District.
Fugro-McClelland
(Midwest) Inc. and ms consultants inc., 1993, Wetland Delineation Report,
prepared for the Stark County Park District.
ms
consultants, inc. and Bromwell & Carrier, Inc., 1996, Sippo Lake - Initial
Feasibility of Rapid Sediment Dewatering, prepared for the Stark County Park
District.
ms
consultants, inc. and Bromwell & Carrier, Inc., 1996, Sippo Lake Sediment
Removal Study: Sediment Removal and Disposal Plan; prepared for the Stark
County Park District.
Northeast
Ohio Four County Regional Planning and Development Organization, 1992, Sippo
Lake Phase I Diagnostic - Feasibility Study.
KEY PERSONNEL INVOLVED IN
SIPPO LAKE DREDGING PROJECT
The dredging of Sippo Lake was a
complex project that required the close cooperation of many individuals. Because of the special problems that were
faced, many persons acted “above and beyond the call of duty” in bringing about
the successful completion of the project.
Some of the key people that were involved in the project are listed
below:
Stark County Park District
Robert Fonte, Park Director
Debbie Graf, Administrative Assistant
David Price, Head Dewatering Plant
Operator
Tony Ulrich, Plant Operator (1997)
Gary McFarland, Plant Operator
(1998)
David Copeland, Bulldozer Operator
(1997)
George Cuckler, Maintenance
Supervisor
ms consultants inc.
R. Richard Fawcett, P.E., Principal
in Charge
William M. Malson, Project Manager
Bromwell & Carrier Inc.
Richard Powers, Principal
Larry Sauls
Midwest Dredge &
Excavating
Eric Wells, President
Jerry Brucker, Project
Superintendent
Dexter Cowan, Dredge Operator
Ben Marrs Jr., Laborer
James Wofford, Laborer
Raymond Givan, Operator
Brian Collins, Laborer
Oakes Land & Excavating
Ed Friedl, Manager
Standard Plumbing &
Heating
Dan Haren, Manager
John Blandford, Superintendent
Allied Colloids Inc.
Don Luke
Preferred Temporary Services
Doug Hill